2009: Albany High School Gymnasium

2009: Albany High School Gymnasium Working with Arrow International once again we fabricated and installed a large portal structure on a green field site.
 

2009: Hubbards Foods Slot Drains

2009: Hubbards Foods Slot Drains These were fabricated and installed around production windows. Sabre built slot drains for one of Hubbard's process areas.
 

2009: Tasti Foods Jacketed Product Lines

2009: Tasti Foods Jacketed Product Lines Sabre fabricated and installed a large spool section of food grade jacketed piping. A combination or orbital and manual tube welding was used and with most sections being made offsite.
 

2008: Pernod Ricard Catwalks Gisbourne

2008: Pernod Ricard Catwalks Gisbourne A reconstruction project post-earthquake damage. These were made in a kitset form and assembled onsite.
 

2008: Visy Recycling Conveyors

2008: Visy Recycling Conveyors

Last minute delays by overseas manufacturers saw Sabre having to manufacture and install 34 conveyors in just over 4 weeks. Coordinating labour and suppliers we managed to make Visy's deadline with just a bit to spare.


 

2007: Vision Senior Living Foot Bridge for Arrow International

2007: Vision Senior Living Foot Bridge for Arrow International

This architecturally designed footbridge left our workshop at the end of November 2007.

It will be a showpiece for Vision Senior Living in Waitakere Auckland.

Installation will be in early January 2008.

The complex curves and svelte lines saw everyone fighting to work on this project.

 

2007: Coca Cola Conveyor Installation for TGW Mechanics GMBH

2007: Coca Cola Conveyor Installation for TGW Mechanics GMBH

Over an 11 month period we have assisted Swiss Log's main contractors, TGW Mechanics, to install an extensive new materials handling system. This has gone into Coca Colas Auckland distribution centre. It has seen us supply a crew of experienced fitters working up to 60 hour weeks.

Various safety fences and working platforms were also commissioned from our manufacturing facility.

 

2007: Bulk Storage Terminals Pipelines

2007: Bulk Storage Terminals Pipelines

Onsite installation of over 200 metres of process piping.

Working inside a bunded hazardous goods area meant ensuring that our health & safety systems were strictly adhered to.

The fully equiped site workshop ensured that our welders could achieve the required standards and deadlines.

 

2006/2007: Catwalks at Nobilo Wine Group for Connell Wagner

2006/2007: Catwalks at Nobilo Wine Group for Connell Wagner Yet another vineyard tank farm installation for Nobilo Wines. This one saw us manufacture and install catwalks for the Corner 50 Winery in the Hawkes Bay. Manufactured in Auckland then shipped to site for installation.
 

2006: Conveyor installation for Independent Liquor

2006: Conveyor installation for Independent Liquor

Over 20 container loads of Krone conveyors were installed by our team over several months.

Systems were installed and running to the customers satisfaction on time.

 

2003: Villa Maria Oruarangi Winery Catwalks

2003: Villa Maria Oruarangi Winery Catwalks

Over 650 metres of catwalk where designed and built by us for Villa Maria's new Oruarangi tank farm. Designed in Solidworks and manufactured in a modular format using zinc sprayed mild steel frames and stainless steel handrails.